  "schema_version": "1.0",
  "language": "en",
  "content_revision": "2026-11-19",
  "verification_note": "A content revision is not a new verification of every source. See source dates and procurement review dates.",
  "project_count": 18,
  "amount_unit": "USD millions",
  "fx": {
    "gtqPerUsd": 7.64682,
    "date": "2026-11-19",
    "source": "https://www.banguat.gob.gt/tipo_cambio/"
  },
  "procurement_review_date": "2026-11-13",
  "notices": [],
  "projects": [
    {
      "id": "ani-01",
      "name": "Radial 6 · CA-1 West–CA-9 South connection",
      "summary": "CA-1 West–CA-9 South connection. The official ANI profile is the scope and cost reference.",
      "sector": "Roads",
      "sector_key": "Carreteras",
      "sector_slug": "roads",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · Guatemala Municipality",
      "location": "Metropolitan area · Sacatepéquez",
      "amount_usd_millions": 158,
      "amount_display": "US$158 M",
      "amount_basis": "Official ANI profile · selected reference",
      "amount_source_date": "Sin fecha publicada · consulta 13 nov. 2026",
      "source_amount": 158,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Traffic studies, road engineering and transaction advisory.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-01/en/",
      "sources": [
        {
          "id": "S21",
          "url": "https://anadie.gob.gt/project/ca1-occidente-ca9-sur/",
          "publisher": "ANI",
          "date": null,
          "title": "Radial 6: institutional project profile"
        },
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-02",
      "name": "North–East Metropolitan Road Connection",
      "summary": "Metropolitan corridor identified for potential PPP development.",
      "sector": "Roads",
      "sector_key": "Carreteras",
      "sector_slug": "roads",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Guatemala metropolitan area",
      "amount_usd_millions": 1227,
      "amount_display": "US$1,227 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 1227,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Metropolitan planning, traffic modelling and road design.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-02/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-03",
      "name": "Public Transport Transfer Centre",
      "summary": "Transport interchange included in the ANI portfolio.",
      "sector": "Mobility",
      "sector_key": "Movilidad",
      "sector_slug": "mobility",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Mixco",
      "amount_usd_millions": 38,
      "amount_display": "US$38 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 38,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Terminal design, transport integration and user research.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-03/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-04",
      "name": "Petén Itzá Transmission System",
      "summary": "Substation and associated transmission infrastructure under assessment.",
      "sector": "Energy",
      "sector_key": "Energía",
      "sector_slug": "energy",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Petén",
      "amount_usd_millions": 200,
      "amount_display": "US$200 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 200,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Electrical engineering, grid studies and environmental analysis.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-04/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-05",
      "name": "San Mateo Ixtatán Transmission System",
      "summary": "Substation and associated line included as an energy initiative.",
      "sector": "Energy",
      "sector_key": "Energía",
      "sector_slug": "energy",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Huehuetenango",
      "amount_usd_millions": 13,
      "amount_display": "US$13 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 13,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Transmission studies, surveying and spatial planning.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-05/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-06",
      "name": "Regional Electricity Transmission Network",
      "summary": "Regional programme of substations and transmission lines.",
      "sector": "Energy",
      "sector_key": "Energía",
      "sector_slug": "energy",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Several departments",
      "amount_usd_millions": 104,
      "amount_display": "US$104 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 104,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Power-system planning, modelling and financial advisory.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-06/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-07",
      "name": "Waste Management and Circular Economy",
      "summary": "One programme covering four territories, counted once.",
      "sector": "Sanitation",
      "sector_key": "Saneamiento",
      "sector_slug": "water-waste",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "MASUR · Sololá · MANCOMUSAC · Gran Ciudad del Sur",
      "amount_usd_millions": 301,
      "amount_display": "US$301 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 301,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Resource-recovery technologies, waste logistics and applied research.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-07/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-08",
      "name": "Regional Airfield Modernisation",
      "summary": "Regional airport package under assessment.",
      "sector": "Airports",
      "sector_key": "Aeropuertos",
      "sector_slug": "airports",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Quetzaltenango · Puerto Barrios · Huehuetenango",
      "amount_usd_millions": 75,
      "amount_display": "US$75 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 75,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Airport planning, aviation engineering and specialist services.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-08/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-09",
      "name": "Femicide and Family Justice Centre",
      "summary": "Specialised public building included in the ANI portfolio.",
      "sector": "Public buildings",
      "sector_key": "Edificación pública",
      "sector_slug": "public-buildings",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Guatemala City",
      "amount_usd_millions": 58,
      "amount_display": "US$58 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 58,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Institutional architecture, accessible design and facilities management.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-09/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "ani-10",
      "name": "Finca El Jaibal Tourism Infrastructure",
      "summary": "Tourism infrastructure with cable transport under assessment.",
      "sector": "Tourism",
      "sector_key": "Turismo",
      "sector_slug": "tourism",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Under assessment",
      "stage_key": "En evaluación",
      "owner": "ANI · contracting authority to confirm",
      "location": "Sololá",
      "amount_usd_millions": 65,
      "amount_display": "US$65 M",
      "amount_basis": "Portfolio estimate · not committed",
      "amount_source_date": "Sep. 2026",
      "source_amount": 65,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "preparation",
      "participation_guidance": "Tourism planning, landscape design and operating models.",
      "next_step": "Ask ANI about scope, available studies and the preparation timetable; identify the applicable formal process before submitting a proposal.",
      "url": "https://guatemalainfrastructure.org/projects/ani-10/en/",
      "sources": [
        {
          "id": "S01",
          "url": "https://agn.gt/guatemala-cuenta-con-un-nuevo-portafolio-de-10-proyectos-por-medio-de-alianzas-publico-privadas/",
          "publisher": "AGN",
          "date": "2026-08-14",
          "title": "ANI portfolio announced in August 2026"
        },
        {
          "id": "S02",
          "url": "https://lahora.gt/lh-economia/esmith/2026/08/13/de-392-necesidades-a-10-proyectos-la-ani-presenta-su-nuevo-portafolio-de-infraestructura-publico-privada/",
          "publisher": "La Hora",
          "date": "2026-08-13",
          "title": "Ten strategic projects: list and locations"
        },
        {
          "id": "S03",
          "url": "https://multimedia.eleconomista.net/epaper/2026/09/63/",
          "publisher": "El Economista · p. 63",
          "date": "2026-09",
          "title": "Strategic portfolio: investment and structure table"
        },
        {
          "id": "S25",
          "url": "https://www.fundesa.org.gt/en/publications/opinion/ani-lanza-10-proyectos-para-el-desarrollo",
          "publisher": "FUNDESA",
          "date": null,
          "title": "FUNDESA: ANI launches ten projects"
        }
      ]
    },
    {
      "id": "epq",
      "name": "Escuintla–Puerto Quetzal Highway",
      "summary": "Approved PPP contract; an existing awarded project.",
      "sector": "Roads",
      "sector_key": "Carreteras",
      "sector_slug": "roads",
      "mechanism": "Public-private partnership (PPP)",
      "mechanism_key": "APP",
      "stage": "Construction reported",
      "stage_key": "Construcción reportada",
      "owner": "CIV · ANI · CONVIA",
      "location": "Escuintla · Pacific corridor",
      "amount_usd_millions": 154,
      "amount_display": "US$154 M",
      "amount_basis": "Reported investment · existing contract",
      "amount_source_date": "Sep. 2026",
      "source_amount": 154,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "delivery",
      "participation_guidance": "Construction suppliers and subcontractors; operations and maintenance preparation.",
      "next_step": "Read the ANI project page and confirm purchasing procedures and supplier requirements with the concessionaire.",
      "url": "https://guatemalainfrastructure.org/projects/epq/en/",
      "sources": [
        {
          "id": "S30",
          "url": "https://anadie.gob.gt/project/autopista-escuintla-puerto-quetzal/",
          "publisher": "ANI",
          "date": null,
          "title": "ANI: current Escuintla–Puerto Quetzal profile"
        }
      ]
    },
    {
      "id": "vas",
      "name": "VAS · Southern Alternative Road",
      "summary": "Operating private road network; a reference for road development and management.",
      "sector": "Roads",
      "sector_key": "Carreteras",
      "sector_slug": "roads",
      "mechanism": "Private",
      "mechanism_key": "Privado",
      "stage": "Operating",
      "stage_key": "En operación",
      "owner": "VAS private operator",
      "location": "Southern metropolitan area",
      "amount_usd_millions": null,
      "amount_display": "To be confirmed",
      "amount_basis": "No comparable CAPEX verified",
      "amount_source_date": null,
      "source_amount": null,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "operation",
      "participation_guidance": "Toll technology, maintenance and user services.",
      "next_step": "Review operator updates and ask about private supplier processes for operating services or announced expansions.",
      "url": "https://guatemalainfrastructure.org/projects/vas/en/",
      "sources": [
        {
          "id": "S15",
          "url": "https://www.vasguatemala.com/noticias",
          "publisher": "VAS",
          "date": null,
          "title": "VAS: operating private road network"
        },
        {
          "id": "S16",
          "url": "https://www.prensalibre.com/economia/vas-cumple-10-anos-y-anuncia-dos-nuevas-opciones-para-los-usuarios-incluida-una-para-facilitar-el-pago/",
          "publisher": "Prensa Libre",
          "date": "2026-08-27",
          "title": "VAS: ten years and three sections"
        }
      ]
    },
    {
      "id": "xochi",
      "name": "Xochi · Corredor de las Flores",
      "summary": "First phase opened to the public in June 2026.",
      "sector": "Roads",
      "sector_key": "Carreteras",
      "sector_slug": "roads",
      "mechanism": "Private",
      "mechanism_key": "Privado",
      "stage": "Operating",
      "stage_key": "En operación",
      "owner": "Xochi private developer and operator",
      "location": "Suchitepéquez · Retalhuleu",
      "amount_usd_millions": null,
      "amount_display": "To be confirmed",
      "amount_basis": "No comparable CAPEX verified",
      "amount_source_date": null,
      "source_amount": null,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "operation",
      "participation_guidance": "Road operations, electronic tolling, maintenance and logistics services.",
      "next_step": "Contact the operator about supplier requirements and potential cooperation linked to operations.",
      "url": "https://guatemalainfrastructure.org/projects/xochi/en/",
      "sources": [
        {
          "id": "S17",
          "url": "https://www.prensalibre.com/guatemala/xochi-abre-oficialmente-y-activa-nueva-conexion-estrategica-en-la-costa-sur/",
          "publisher": "Prensa Libre",
          "date": "2026-06-14",
          "title": "Xochi: opening to the public"
        }
      ]
    },
    {
      "id": "verde",
      "name": "Corredor Verde",
      "summary": "Private connection between San Cristóbal and the Periférico; construction reported.",
      "sector": "Roads",
      "sector_key": "Carreteras",
      "sector_slug": "roads",
      "mechanism": "Private",
      "mechanism_key": "Privado",
      "stage": "Construction reported",
      "stage_key": "Construcción reportada",
      "owner": "Corredor Verde, S.A. · applicable municipal permits",
      "location": "Mixco · Guatemala City zone 11",
      "amount_usd_millions": 65.3866574602253,
      "amount_display": "≈ US$65.4 M",
      "amount_basis": "Announced minimum · approximate USD equivalent",
      "amount_source_date": "Jul. 2026",
      "source_amount": 500,
      "source_currency": "GTQ",
      "converted_to_usd": true,
      "participation_status": "delivery",
      "participation_guidance": "Civil engineering, structures, drainage and construction supplies.",
      "next_step": "Ask the promoter about work scope and private procurement procedures before offering supplies or services.",
      "url": "https://guatemalainfrastructure.org/projects/verde/en/",
      "sources": [
        {
          "id": "S18",
          "url": "https://lahora.gt/nacionales/hloarca/2026/07/05/de-san-cristobal-a-zona-11-en-15-minutos-avanza-construccion-de-nueva-ruta-con-paso-subterraneo/",
          "publisher": "La Hora",
          "date": "2026-07-05",
          "title": "Corredor Verde: construction and announced investment"
        }
      ]
    },
    {
      "id": "aero",
      "name": "AeroMetro · municipal concession",
      "summary": "Cable transport concession; construction and financial close reported.",
      "sector": "Mobility",
      "sector_key": "Movilidad",
      "sector_slug": "mobility",
      "mechanism": "Municipal concession",
      "mechanism_key": "Concesión municipal",
      "stage": "Construction reported",
      "stage_key": "Construcción reportada",
      "owner": "Guatemala Municipality · Cablevía and concession group; coordination with Mixco",
      "location": "Guatemala · Mixco",
      "amount_usd_millions": 220,
      "amount_display": "US$220 M",
      "amount_basis": "Developer’s published estimate",
      "amount_source_date": "Página consultada nov. 2026",
      "source_amount": 220,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "delivery",
      "participation_guidance": "Electromechanical systems, stations, urban integration and operations training.",
      "next_step": "Ask the concessionaire about delivery stages and supplier-chain requirements.",
      "url": "https://guatemalainfrastructure.org/projects/aero/en/",
      "sources": [
        {
          "id": "S12",
          "url": "https://www.aerometro.gt/",
          "publisher": "Cablevía / AeroMetro",
          "date": null,
          "title": "AeroMetro: project developer"
        },
        {
          "id": "S13",
          "url": "https://www.deloitte.com/latam/es/services/financial-advisory/perspectives/deloitte-trusted-advisor-aerometro-guatemala.html",
          "publisher": "Deloitte",
          "date": "2026",
          "title": "AeroMetro: financial close"
        },
        {
          "id": "S14",
          "url": "https://lahora.gt/lh-economia/hloarca/2026/02/05/del-trebol-a-la-zona-9-sin-trafico-la-constructora-del-aerometro-promete-conectar-estos-puntos-en-18-meses/",
          "publisher": "La Hora",
          "date": "2026-02-05",
          "title": "AeroMetro: construction and concession model"
        },
        {
          "id": "S23",
          "url": "https://www.congreso.gob.gt/assets/uploads/info_legislativo/diario_de_sesiones/d3731-diario-final-so_076_24-11-2021.pdf",
          "publisher": "Congreso de la República",
          "date": "2021-11-24",
          "title": "AeroMetro: legislative concession record"
        }
      ]
    },
    {
      "id": "uk",
      "name": "Metro Riel · Guatemala–UK cooperation",
      "summary": "Agreement signed in July 2026 to support project preparation and planning.",
      "sector": "Mobility",
      "sector_key": "Movilidad",
      "sector_slug": "mobility",
      "mechanism": "Government-to-government cooperation (G2G)",
      "mechanism_key": "G2G",
      "stage": "Early preparation",
      "stage_key": "Preparación temprana",
      "owner": "Guatemalan and UK governments · joint working group; implementing entity to be specified",
      "location": "Guatemala metropolitan area",
      "amount_usd_millions": null,
      "amount_display": "To be confirmed",
      "amount_basis": "No current CAPEX validated for this cooperation",
      "amount_source_date": null,
      "source_amount": null,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "cooperation",
      "participation_guidance": "Rail studies, urban integration and academic cooperation.",
      "next_step": "Review the cooperation framework and confirm the implementing body, scope and published procedures before preparing a bid.",
      "url": "https://guatemalainfrastructure.org/projects/uk/en/",
      "sources": [
        {
          "id": "S10",
          "url": "https://www.gov.uk/government/news/guatemala-chooses-uk-as-partner-for-metro-riel",
          "publisher": "British Embassy · GOV.UK",
          "date": "2026-07-14",
          "title": "Guatemala chooses UK as Metro Riel partner"
        },
        {
          "id": "S11",
          "url": "https://agn.gt/que-dice-el-memorando-firmado-entre-guatemala-y-el-reino-unido-sobre-el-proyecto-metrorriel",
          "publisher": "AGN",
          "date": "2026-07-17",
          "title": "Scope of Guatemala–UK memorandum"
        },
        {
          "id": "S32",
          "url": "https://guatemala.gob.gt/presidente-bernardo-arevalo-presenta-resultados-de-fase-0-y-hoja-de-ruta-del-proyecto-metroriel/",
          "publisher": "Secretaría de Comunicación Social · Gobierno de Guatemala",
          "date": "2026-10-30",
          "title": "Metro Riel: Phase 0 results and roadmap"
        }
      ]
    },
    {
      "id": "us-port",
      "name": "Puerto Quetzal · USACE cooperation",
      "summary": "Cooperation on port modernisation and rail connection studies.",
      "sector": "Ports and logistics",
      "sector_key": "Puertos y logística",
      "sector_slug": "ports-logistics",
      "mechanism": "Government-to-government cooperation (G2G)",
      "mechanism_key": "G2G",
      "stage": "Early preparation",
      "stage_key": "Preparación temprana",
      "owner": "Mindef · CIV · USACE; port coordination with EPQ to be specified in the instruments",
      "location": "Puerto Quetzal · Escuintla",
      "amount_usd_millions": null,
      "amount_display": "To be confirmed",
      "amount_basis": "No component-level CAPEX validated",
      "amount_source_date": null,
      "source_amount": null,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "cooperation",
      "participation_guidance": "Port engineering, maritime studies and technical training.",
      "next_step": "Ask EPQ about the public scope of cooperation and confirm which institution handles each study or procurement.",
      "url": "https://guatemalainfrastructure.org/projects/us-port/en/",
      "sources": [
        {
          "id": "S08",
          "url": "https://agn.gt/unidos-estamos-construyendo-oportunidades-alianza-guatemala-ee-uu-apuesta-por-carreteras-y-puertos/",
          "publisher": "AGN",
          "date": "2026-01-15",
          "title": "USACE cooperation: letters of acceptance"
        }
      ]
    },
    {
      "id": "us-road",
      "name": "Road programme · USACE cooperation",
      "summary": "Six announced interventions; current progress and packages require confirmation.",
      "sector": "Roads",
      "sector_key": "Carreteras",
      "sector_slug": "roads",
      "mechanism": "Government-to-government cooperation (G2G)",
      "mechanism_key": "G2G",
      "stage": "Early preparation",
      "stage_key": "Preparación temprana",
      "owner": "Mindef · CIV · USACE",
      "location": "Several departments",
      "amount_usd_millions": null,
      "amount_display": "To be confirmed",
      "amount_basis": "Cooperation funding not treated as project-level CAPEX",
      "amount_source_date": null,
      "source_amount": null,
      "source_currency": "USD",
      "converted_to_usd": false,
      "participation_status": "cooperation",
      "participation_guidance": "Road studies, interchange engineering and technical assistance.",
      "next_step": "Ask CIV for public information on components, studies and the procuring entity; follow published procedures.",
      "url": "https://guatemalainfrastructure.org/projects/us-road/en/",
      "sources": [
        {
          "id": "S08",
          "url": "https://agn.gt/unidos-estamos-construyendo-oportunidades-alianza-guatemala-ee-uu-apuesta-por-carreteras-y-puertos/",
          "publisher": "AGN",
          "date": "2026-01-15",
          "title": "USACE cooperation: letters of acceptance"
        },
        {
          "id": "S09",
          "url": "https://agn.gt/cuerpo-de-ingenieros-del-ejercito-de-estados-unidos-ya-se-organiza-para-la-construccion-de-proyectos-viales-prioritarios-en-guatemala/",
          "publisher": "AGN",
          "date": "2026-05-25",
          "title": "USACE: six announced road interventions"
        }
      ]
    }
  ]
}